Home › EV Charging Rules › Puducherry
EV charging station rules in Puducherry
Union Territory · official routes, cited to primary sources
EV charging in Puducherry — the official route
JERC for the State of Goa and Union Territories is the electricity regulator for this jurisdiction; its formal orders and regulations control tariff and regulated supply matters.
The latest located formal retail-tariff baseline is the MYT order for FY 2025-26 to FY 2029-30 for Electricity Department, Government of Puducherry; the annual schedule, later corrigenda and adjustment orders must be read together before pricing.
FY 2026-27: LTEV-I energy charge INR 6.05/kVAh and fixed charge INR 35/kVA/month; HTS-VI energy charge INR 6.05/kVAh and fixed charge INR 100/kVA/month. These are approved base-schedule amounts; the actual bill still requires category, voltage, later-order, adjustment, duty/tax and site-specific confirmation.
The official JERC tariff-order category page is the control point for later review, true-up, amendment or corrigendum orders; the archived MYT order is not a substitute for that later-order check.
Electricity Department, Government of Puducherry is the located distribution-utility route. Exact office/section, available voltage, sanctioned-load pathway and network feasibility must be confirmed from the complete site address.
New connection, load enhancement, meter, demand note, agreement, testing and energisation must use the current utility process and forms; the portal may require login, payment or manual submission.
JERC standards-of-performance material is a planning reference for service stages and timelines, but any quoted completion date remains subject to a complete application, right-of-way, augmentation and statutory inspection conditions.
EV charging-station operation is de-licensed only while the operator follows the applicable national guidelines and other laws.
A separate meter and the applicable commission-approved tariff pathway must be confirmed for the charging arrangement.
AC and DC installations must meet the relevant CEA electrical-safety protections, testing and record-retention duties; final design and energisation require qualified professionals and competent-authority acceptance where triggered.
Public charging rates and service charges must be displayed as required by the national charging guideline; applicable GST and land-cost treatment must not be guessed.
Public-site layouts require an accessibility screen for route, bay, interface, payment and assistance arrangements, alongside local land/building/fire approvals.
No current Union Territory-specific EV policy or formal State/UT Nodal Agency designation was established in the located official evidence; confirm the lead department and any live incentive or tender program in writing.
Retail tariff for the Electricity Department, Puducherry is determined by the Joint Electricity Regulatory Commission for Goa and Union Territories for the 4th multi-year tariff control period FY 2025-26 to FY 2029-30, by order dated 24 September 2025, which also trues up FY 2023-24.
The Electricity Department Puducherry tariff structure contains a dedicated low-tension category 'LTEV-I (EV charging station)', carried through the Commission's category-wise consumer, sales and revenue tables for the 4th MYT control period.
The LTEV-I EV charging station category records nil consumers, nil sales and nil revenue across the Commission's tables for FY 2025-26 to FY 2029-30. The category exists in the tariff structure but had no consumers billed under it at the date of the order.
Standard voltage of supply is set by contracted load, with EV charging stations given their own bands: an EV Charging Station with contracted load exceeding 5 kW and up to and including 167 kVA (150 kW) takes 3-phase 4-wire supply at 440 V (low tension), while all other installations are limited to 100 kVA of contracted load at low tension. An EV Charging Station with contracted load above 167 kVA (150 kW) and up to 5,000 kVA takes high tension at 6.6 kV, 11 kV, 22 kV or 33 kV, and contracted load above 5,000 kVA takes extra high tension at 66 kV and above.
Timelines for releasing a new connection or additional load where supply can be provided from the existing network, from receipt of an application complete in all respects: within 3 days in metro cities, 7 days in urban and municipal areas, 15 days in rural areas, and 30 days in rural areas of islands. Where extension works, enhancement of transformer capacity, extension of distribution mains or commissioning of a new substation is required, the licensee shall supply immediately after such extension or commissioning and within a period not exceeding 90 days.
If a distribution licensee fails to supply electricity within the period specified in the Supply Code Regulations it is liable to a penalty not exceeding five hundred rupees for each day of default.
An applicant may submit the connection application in hard copy or by electronic means; where a hard copy is submitted it must be scanned and uploaded, and an acknowledgement carrying the registration number must be issued within 24 hours of receipt of a complete application. Applications for new connections up to 10 kW must carry a photograph of the applicant, identity proof, and proof of ownership or occupancy of the premises; above 10 kW and for modifications, further documents apply. Where an agreement between licensee and consumer is required it forms part of the application and no separate agreement is needed.
No connection shall be given without a meter, and that meter must be a smart pre-payment meter or a pre-payment meter; any exception requires the Commission's approval with recorded justification. After a smart meter is installed no penalty may be imposed on the consumer for maximum demand recorded before the installation date. Where maximum demand recorded by the smart meter exceeds the sanctioned load in a month, that billing cycle is calculated on the actual recorded maximum demand and the consumer must be informed by SMS or mobile application, with sanctioned-load revision following where the recorded demand has exceeded the sanctioned limit at least three times in a financial year.
Who regulates and supplies in Puducherry
| Authority type | Authority | Role | Official portal | Source |
|---|---|---|---|---|
| Regulator | Joint Electricity Regulatory Commission for Goa and UTs | Tariff, supply regulation, standards of performance and consumer regulation | https://jercuts.gov.in/ | [PY-JERC-ORDERS-WEB-001] |
| Distribution utility | Electricity Department, Government of Puducherry | Service-area confirmation, new/load-enhancement connection, metering, demand note, testing and energisation | https://electricity.py.gov.in/ | [PY-PED-WEB-001] |
| Policy/nodal agency gap | Puducherry Administration - current State/UT Nodal Agency designation not located | EV policy and charging coordination | [NAT-MOP-2024-001] | |
| Electrical inspectorate | Chief Electrical Inspector / Electrical Inspectorate serving Puducherry | Electrical-safety approval/inspection where triggered | [NAT-CEA-2023-001] | |
| Fire/local authority | Fire service and competent local/planning/building authority | Fire, building, land use, parking, access and occupancy approvals | [NAT-CEA-2023-001] | |
| Road/highway authority | Competent road owner / highway authority | Access, setback, signage and right-of-way approval | [NAT-MOP-2024-001] |
Which DISCOM serves your site in Puducherry
| District / region | Likely utility | Basis | Must confirm | Source |
|---|---|---|---|---|
| Puducherry | PED | Official JERC/utility jurisdiction route | Confirm exact section/office and network for full address | [PY-PED-WEB-001] |
| Karaikal | PED | Official JERC/utility jurisdiction route | Confirm exact section/office and network for full address | [PY-PED-WEB-001] |
| Yanam | PED | Official JERC/utility jurisdiction route | Confirm exact section/office and network for full address | [PY-PED-WEB-001] |
| Mahe | PED | Official JERC/utility jurisdiction route | Confirm exact section/office and network for full address | [PY-PED-WEB-001] |
Fees, deposits and timelines in Puducherry
| Item | Value | Basis | When | Caveat | Source |
|---|---|---|---|---|---|
| FY 2026-27 EV energy and fixed/demand charges | FY 2026-27: LTEV-I energy charge INR 6.05/kVAh and fixed charge INR 35/kVA/month; HTS-VI energy charge INR 6.05/kVAh and fixed charge INR 100/kVA/month. | Official approved base schedule | FY 2026-27 | Confirm use case, voltage, later orders, adjustment charges and duty/tax before reliance | [PY-JERC-TARIFF-2025-001] |
| EV charging tariff category | LTEV/HTS-VI or HT-VI as applicable under the controlling schedule | Official control | Before financial model | Confirm public/captive/fleet/workplace/residential use, connected demand and supply voltage | [PY-JERC-TARIFF-2025-001] [PY-JERC-ORDERS-WEB-001] |
| Energy and fixed/demand charge currency | Base amounts above are not an all-in delivered cost | Official variable | Billing period | Check later review/true-up/amendment orders, adjustment charges, duty/tax, minimum billing and meter treatment | [PY-JERC-TARIFF-2025-001] |
| Time-of-day / power-factor terms | Requires category and meter confirmation | Official variable | Billing period | Model only after utility acceptance | [PY-JERC-TARIFF-2025-001] |
| Application / processing fee | Not safely established as a current universal amount | Live confirmation | At submission | Use live form/portal demand | [PY-GO-CONN-2026-001] |
| Security deposit | Project and category specific | Live confirmation | Demand note | Do not estimate as an approval | [PY-GO-CONN-2026-001] |
| Service line / augmentation / transformer | Site-specific utility estimate | Live confirmation | After feasibility | May control feasibility and COD | [PY-GO-CONN-2026-001] |
| Electrical inspection / testing | Trigger and fee require confirmation | Live confirmation | Before energisation | Confirm authority and licensed-party scope | [NAT-CEA-2023-001] |
| Local/fire/building/road fees | Site-specific | Live confirmation | Before works/opening | Identify all competent authorities | |
| Connection timeline | No unconditional date quoted | Planning control | Complete application plus dependencies | Right-of-way, augmentation and inspection can extend timing | [PY-JERC-SOP-WEB-001] |
What is still unconfirmed in Puducherry
- Confirm exact serving office/section and preliminary supply point for the complete address.
- Confirm the current tariff category, energy and fixed/demand charges, ToD/power-factor terms, duty/tax and adjustment charges for the actual public/captive/fleet/workplace use.
- Confirm whether a new connection, load enhancement, separate meter, LT/HT supply or dedicated transformer is required.
- Provide the current form/upload list, application fee, security deposit, service-line/augmentation basis and written timeline.
- Identify the current UT nodal agency/lead department for EV charging and any live incentive or tender route.
- Confirm electrical-inspectorate jurisdiction, approval threshold, drawing/test requirements, fee and inspection stage.
- Confirm fire, building/land-use, access, signage and road/highway approvals for the exact parcel.
- Confirm coastal/island logistics, corrosion/weather/flood design inputs, spares and emergency-response constraints where applicable.
- Extract the EV charging station tariff category and rates from PY-TARIFF-2025-001 and confirm whether a dedicated EV category exists for PED Puducherry.