EV Infra Advisory

HomeEV Charging RulesGoa › Getting an electricity connection for a charger in Goa

EV Charging Connection Process in Goa

Part of the Goa EV charging reference · last verified 2026-08-14

← Full Goa guide

Getting an electricity connection for a charger in Goa

GED's portal routes LT new connections up to 90 kW and HT new connections above 90 kW and offers load change forms tracking and document upload.

Official utility guidance · GED · High · verified 2026-07-31 · confirm: Yes - reconcile EV LT threshold · [GA-GED-PORTAL-WEB-001]

Timelines for releasing a new connection or additional load where supply can be provided from the existing network, from receipt of an application complete in all respects: within 3 days in metro cities, 7 days in urban and municipal areas, 15 days in rural areas, and 30 days in rural areas of islands. Where extension works, enhancement of transformer capacity, extension of distribution mains or commissioning of a new substation is required, the licensee shall supply immediately after such extension or commissioning and within a period not exceeding 90 days.

Official requirement · Joint Electricity Regulatory Commission for the State of Goa and Union Territories · High · verified 2026-08-14 · [GA-SC-AMD3-2024-001]

If a distribution licensee fails to supply electricity within the period specified in the Supply Code Regulations it is liable to a penalty not exceeding five hundred rupees for each day of default.

Official requirement · Joint Electricity Regulatory Commission for the State of Goa and Union Territories · High · verified 2026-08-14 · [GA-SC-AMD3-2024-001]

An applicant may submit the connection application in hard copy or by electronic means; where a hard copy is submitted it must be scanned and uploaded, and an acknowledgement carrying the registration number must be issued within 24 hours of receipt of a complete application. Applications for new connections up to 10 kW must carry a photograph of the applicant, identity proof, and proof of ownership or occupancy of the premises; above 10 kW and for modifications, further documents apply. Where an agreement between licensee and consumer is required it forms part of the application and no separate agreement is needed.

Official requirement · Joint Electricity Regulatory Commission for the State of Goa and Union Territories · High · verified 2026-08-14 · [GA-SC-AMD3-2024-001]

No connection shall be given without a meter, and that meter must be a smart pre-payment meter or a pre-payment meter; any exception requires the Commission's approval with recorded justification. After a smart meter is installed no penalty may be imposed on the consumer for maximum demand recorded before the installation date. Where maximum demand recorded by the smart meter exceeds the sanctioned load in a month, that billing cycle is calculated on the actual recorded maximum demand and the consumer must be informed by SMS or mobile application, with sanctioned-load revision following where the recorded demand has exceeded the sanctioned limit at least three times in a financial year.

Official requirement · Joint Electricity Regulatory Commission for the State of Goa and Union Territories · High · verified 2026-08-14 · [GA-SC-AMD3-2024-001]

Also see

What next