EV charging station rules in Haryana

State · official routes, cited to primary sources

20 requirements8 sources5 archived documents11 open questionsConfidence: HighLast verified: 2026-08-13

EV charging in Haryana — the official route

EV battery charging is de-licensed nationally subject to applicable technical safety and operating requirements.

Official requirement · Ministry of Power · High · verified 2026-07-31 · confirm: Yes - site approvals · [NAT-MOP-2018-001]

Haryana EV Policy 2022 became effective on 10-07-2022 for a stated five-year period.

Official requirement · Industries and Commerce Department · High · verified 2026-07-31 · confirm: Yes - terminal date/extension · [HR-EV-2022-001]

Town and Country Planning must include charging-infrastructure provisions in covered building types and amend the Haryana Building Code 2017 accordingly.

Official policy requirement · Town and Country Planning Department · High · verified 2026-07-31 · confirm: Yes · [HR-EV-2022-001]

Charging infrastructure is to be developed in existing and new public buildings public parking and State Transport bus depots/sub-depots.

Official policy requirement · Government of Haryana · High · verified 2026-07-31 · confirm: Yes - project implementation · [HR-EV-2022-001]

Policy targets fast charging and swapping on highways/prominent roads every 30 km.

Official policy statement · Government of Haryana · High · verified 2026-07-31 · confirm: Yes - implementing plan · [HR-EV-2022-001]

Battery swapping stations are encouraged with due intimation to the distribution licensee and policy states the public-charging tariff rebate also applies to them.

Official policy statement · DISCOMs/Government of Haryana · Medium · verified 2026-07-31 · confirm: Yes - critical · [HR-EV-2022-001]

The policy offers a first-100 battery-swapping-station capital subsidy of 20% of FCI up to ₹10 lakh where FCI exceeds ₹50 lakh outside covered central-scheme areas.

Official policy incentive · Industries and Commerce Department · High · verified 2026-07-31 · confirm: Yes · [HR-EV-2022-001]

The policy offers a first-200 privately owned public-charging-station capital subsidy of 20% of FCI up to ₹5 lakh where FCI exceeds ₹25 lakh outside covered central-scheme areas.

Official policy incentive · Industries and Commerce Department · High · verified 2026-07-31 · confirm: Yes · [HR-EV-2022-001]

The policy offers a first-2000 building/site charging subsidy of 20% FCI up to ₹50000 subject to population/footfall and at least ten charging units.

Official policy incentive · Industries and Commerce Department · High · verified 2026-07-31 · confirm: Yes · [HR-EV-2022-001]

For FY 2026-27 EV charging stations supplied at HT are listed at CoS-HT ₹7.24 per unit.

Official requirement · UHBVN/HERC · High · verified 2026-07-31 · confirm: Yes - DHBVN/address/bill additions · [HR-TARIFF-2026-001]

For FY 2026-27 EV charging stations supplied at LT are listed at CoS-LT ₹7.48 per unit.

Official requirement · UHBVN/HERC · High · verified 2026-07-31 · confirm: Yes - DHBVN/address/bill additions · [HR-TARIFF-2026-001]

The FY 2026-27 EV fixed-charge and MMC cells are blank; written confirmation is required before treating them as Nil.

Official table interpretation · UHBVN/HERC · Medium · verified 2026-07-31 · confirm: Yes - critical · [HR-TARIFF-2026-001]

The FY 2026-27 schedule excludes electricity duty municipal tax panchayat tax and FSA which may be payable in addition.

Official requirement · UHBVN/HERC · High · verified 2026-07-31 · confirm: Yes - current rates · [HR-TARIFF-2026-001]

A green-energy premium of ₹0.88 per unit above normal tariff is listed for consumers opting for green energy.

Official requirement · UHBVN/HERC · High · verified 2026-07-31 · confirm: Yes - eligibility/contract · [HR-TARIFF-2026-001]

UHBVN serves northern Haryana and DHBVN southern Haryana; the exact SDO/subdivision must be confirmed from the full address.

Official guidance · UHBVN/DHBVN · High · verified 2026-07-31 · confirm: Yes - exact office · [HR-UHBVN-WEB-001]

DHBVN publishes its new-connection application route (econnection.dhbvn.org.in), connection-related services, downloadable forms, new-connection status tracking, commercial sales circulars, a Right-to-Service timelines and authorities schedule, an electricity safety code and an office locator. An application must be routed to DHBVN only after the full site address and the serving office or subdivision are confirmed.

Official portal guidance · Dakshin Haryana Bijli Vitran Nigam · Medium · verified 2026-08-13 · confirm: Yes - current forms, service charges and subdivision must be confirmed · [HR-DHBVN-WEB-001]

The Haryana Enterprises Promotion Centre is the state single-roof clearance platform, offering a composite application form, procedure checklists, building-plan status, the central inspection system, land availability and incentive tools. The EV Policy 2022 and related notices are published there. Policy incentives must not be treated as open or automatically payable without confirming the live scheme window, eligibility and budget.

Official portal guidance · Government of Haryana, Department of Industries and Commerce · Medium · verified 2026-08-13 · confirm: Yes - scheme window, eligibility and budget availability · [HR-HEPC-WEB-001]

Statutory time limits for release of a new connection, additional load or demand, in working days from receipt of a complete application with charges and documents: 30 days where supply is feasible from the existing network; 30 days for LT connections requiring network expansion or enhancement; 71 days for 11 kV connections; 97 days for 33 kV connections; and 167 days for connections above 33 kV.

Official requirement · Dakshin Haryana Bijli Vitran Nigam · High · verified 2026-08-13 · [HR-RTS-2014-001]

For release of a new connection the designated officer is the SDO (Operations), with the XEN (Operations) as first grievance redressal authority and the SE (Operations) as second, for LT and 11 kV connections. For 33 kV and above the designated officer is the XEN (Operations), with the SE and then the Chief Engineer (Operations). Applications are made through the Antyodaya Saral portal (saralharyana.gov.in) or econnection.dhbvn.org.in.

Official requirement · Dakshin Haryana Bijli Vitran Nigam · High · verified 2026-08-13 · [HR-RTS-2014-001]

Related statutory time limits: transfer of title or change of category within 7 days; conversion of LT single-phase to three-phase or vice versa within 30 days; shifting of a meter or service connection within 15 days; shifting of LT or HT lines up to and above 11 kV within 45 days; shifting of a transformer within 60 days; and resolution of a disputed bill within 24 hours, or 7 days where additional information is required.

Official requirement · Dakshin Haryana Bijli Vitran Nigam · High · verified 2026-08-13 · [HR-RTS-2014-001]

Who regulates and supplies in Haryana

Authority typeAuthorityRoleOfficial portalSource
RegulatorHaryana Electricity Regulatory CommissionTariff regulations and licensinghttps://herc.gov.in/[HR-TARIFF-2026-001]
Policy departmentIndustries and Commerce DepartmentEV Policy 2022 and industry incentiveshttps://haryanaindustries.gov.in/[HR-EV-2022-001]
Single-window agencyHaryana Enterprises Promotion CentreComposite Application Form approvals and investor facilitationhttps://investharyana.in/[HR-HEPC-WEB-001]
Distribution utilityUttar Haryana Bijli Vitran NigamDistribution/new connection in northern Haryanahttps://www.uhbvn.org.in/[HR-UHBVN-WEB-001]
Distribution utilityDakshin Haryana Bijli Vitran NigamDistribution/new connection in southern Haryanahttps://www.dhbvn.org.in/[HR-DHBVN-WEB-001]
Renewable-energy agencyHAREDA/NRE DepartmentPolicy coordination for government EV deployment and awarenesshttps://hareda.gov.in/[HR-EV-2022-001]
Building/planning authorityTown and Country Planning DepartmentBuilding-code and charging-space provisionshttps://tcpharyana.gov.in/[HR-EV-2022-001]
Electrical safety authorityChief Electrical Inspector HaryanaElectrical plan/inspection/energization oversight where triggeredhttps://investharyana.in/[HR-HEPC-WEB-001]
Fire/local authorityHaryana Fire Service/ULB/HSIIDC/TCP authorityFire building land road and local approvalshttps://investharyana.in/[HR-HEPC-WEB-001]

Which DISCOM serves your site in Haryana

Utility allocation is indicative. Confirm the exact division and service point from the full site address before applying.
District / regionLikely utilityBasisMust confirmSource
PanchkulaUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
AmbalaUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
YamunanagarUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
KurukshetraUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
KarnalUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
PanipatUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
KaithalUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
RohtakUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
JhajjarUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
SonipatUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
JindUHBVNNorthern Haryana utility screenConfirm exact SDO/subdivision[HR-UHBVN-WEB-001]
GurugramDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
FaridabadDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
PalwalDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
NuhDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
RewariDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
MahendragarhDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
BhiwaniDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
Charkhi DadriDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
HisarDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
FatehabadDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]
SirsaDHBVNSouthern Haryana utility screenConfirm exact SDO/subdivision[HR-DHBVN-WEB-001]

Fees, deposits and timelines in Haryana

Values marked indicative or variable are not official quotations.
ItemValueBasisWhenCaveatSource
EV charging HT energy₹7.24/unit CoS-HTOfficial2026-04-01 to 2027-03-31Confirm DHBVN implementation and all additions.[HR-TARIFF-2026-001]
EV charging LT energy₹7.48/unit CoS-LTOfficial2026-04-01 to 2027-03-31Confirm DHBVN implementation and all additions.[HR-TARIFF-2026-001]
EV fixed chargeBlank in tariff tableRequires written confirmationFY 2026-27Do not infer Nil solely from blank cell.[HR-TARIFF-2026-001]
EV MMCBlank in tariff tableRequires written confirmationFY 2026-27Do not infer Nil solely from blank cell.[HR-TARIFF-2026-001]
Electricity duty/municipal/panchayat tax/FSAExcluded from schedule and potentially additionalOfficialFY 2026-27Obtain current rates/exemptions and billing treatment.[HR-TARIFF-2026-001]
Optional green energy premium₹0.88/unit above normal tariffOfficialFY 2026-27Confirm product eligibility and contract.[HR-TARIFF-2026-001]
Public charging incentive20% FCI up to ₹5 lakh; first 200; FCI over ₹25 lakhOfficial policyStated policy period/conditionsAvailability and remaining allocation unconfirmed.[HR-EV-2022-001]
Battery swapping incentive20% FCI up to ₹10 lakh; first 100; FCI over ₹50 lakhOfficial policyStated policy period/conditionsAvailability and remaining allocation unconfirmed.[HR-EV-2022-001]
Building/site charging incentive20% FCI up to ₹50000; first 2000; threshold conditionsOfficial policyStated policy period/conditionsConfirm interpretation and availability.[HR-EV-2022-001]
Security deposit/service chargesVariable by load voltage category and worksLive utility estimateNew connection/load enhancementCurrent schedule and demand note required.
Connection timelineNot fixed in this evidence setRequires authority confirmationComplete application through energizationUse live standards of performance and project-specific works plan.

What is still unconfirmed in Haryana

Published deliberately. These are the points we have not been able to verify from a primary source, and what we would confirm before advising on a site.

Go deeper

EV Charging Tariff in Haryana1 entry · read the full pageEV Charging Connection Process in Haryana4 entries · read the full pageEV Charging Safety Approvals in Haryana2 entries · read the full pageEV Charging Subsidies in Haryana2 entries · read the full pageEV Charging Connection Forms in Haryana8 entries · read the full page